Pioneer Crossing Update: 4/26/2010

Monday, April 26th, 2010

I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – With traffic now moved to the south side of Main Street, please remember that lanes are narrowed and all left turns into the business areas between State Street and Kawakami Drive are to be made only at signalized intersections.
April 21-May 7: Watch for lane restrictions and shifts on Main Street at U.S. 89 as crews reconstruct the curb, gutter and sidewalks on the south east corner of the intersection.
Ongoing: The right-in turns into Main Street Plaza and the Alpine Shopping Center from westbound Main Street are closed to allow crews to reconstruct the north half of Main Street between U.S. 89 and I-15. The closure will be in place until mid-August. Motorists should use Kawakami Drive to access the shopping centers.
1020 West is closed as crews install utilities down the center of 1020 West and reconstruct the roadway. The closure will be in place through early May. Motorists will need to use 900 West for access to homes and businesses on 1020 West.
Work is underway at the bridge farm location, north of 900 West. Flaggers will be posted at 900 West to guide drivers through the work zone. Work will continue through the night so expect some construction noise.
Work on abutments and bridge support columns for the north bridge of the new Diverging Diamond Interchange (DDI) continues near the interchange.
April 26: The southbound on-ramp will be closed from 11 p.m. to 6 a.m. while workers pave the remaining portion of the on-ramp. The closure date may change depending on weather.
May 1: Southbound I-15 will be restricted to one lane from 11 p.m. Saturday, to 6 a.m. Sunday as crews reconfigure and re-stripe southbound lanes. All southbound traffic will be redirected through the HOV lane during the work.Southbound on and off-ramps at American Fork Main Street will be closed. Access across the Main Street bridge over I-15 will also be restricted during this time. Motorists are advised to use Lehi Main Street.
Ongoing: I-15 will be restricted to two lanes in each direction nightly from 8 p.m. to 6 a.m. for bridge construction and paving. Please expect periodic restrictions at the on- and off-ramps during these hours. Lane restrictions will continue through the spring. Motorists should anticipate moderate travel delays.
I-15 Travel Lane Changes: The I-15 travel lanes near the American Fork Main Street interchange are narrowed to 11 feet and 10.5 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
For information about I-15 CORE construction activities near American Fork Main Street please visit www.i15core.utah.gov.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – Work to set girders for the Mill Pond Bridge is complete. Work on the bridge deck structure continues. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone. This work will continue through spring.
South Area – Work on retaining walls will continue through late May.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until mid-summer 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): April 26- Mid-June: 300 East will be closed for utility work and construction of the new intersection. All through traffic will be detoured along Center Street. Other routes are available for area residents affected by the closure.
500 West to 300 East Area (Lehi): April 23: Center Street will reopen at the Pioneer Crossing intersection.
1100 West to 500 West Area (Lehi): Work on sidewalks will begin this week.
1100 West is open.
April 23- Mid-June: 500 West will be closed for utility work and construction of the new intersection. All through traffic will be detoured along 1100 West, Center Street and 1900 South. Other routes are available for area residents affected by the closure.
1700 West to 1100 West Area (Lehi): Construction of the trail undercrossing for the future Dry Creek trail continues. The top portion of the trail undercrossing has been poured.
Work on noise walls will continue through early May.
Work will continue on footings and walls for the Dry Creek box culvert through May.
April 26- May 5: 1700 West will be closed near the Pioneer Crossing intersection to allow for crews to place the final layer of asphalt and raise utility manholes. Motorists should use 2300 West.
2300 West to 1700 West Area (Lehi): Work to install utilities will continue. Crews will begin placing top soil in the park strip in May. Crews will begin installing the posts for the noise walls in early May.
2300 West is open
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Work to place top soil in the medians will continue through early May. Crews will begin planting plants and trees once the topsoil is complete.
Jordan River Bridge Area – Crews continue to build retaining walls for the river bridge. Placement of the concrete bridge deck is complete. Work on the bridge approaches will continue through late April.
Work on the Jordan River Parkway Trail crossing at the new Pioneer Crossing bridge continues. Meanwhile, the Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration in early summer.
Redwood Road to Jordan River Area – Work continues on foundations for the permanent signs. Paving will continue through late April. Work to place curb and gutter will begin this week.
General Project Information General work hours are between 7 a.m. and 5 p.m. Monday through Saturday. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents – especially children – to keep out of the construction area.

2100 North Project Update: 4/21/10

Wednesday, April 21st, 2010

2100 North Project Update: 4/21/10
The following are planned activities for the coming week. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change. For safety reasons, one southbound lane on Redwood Road will be closed for several hours during the day on Thursday, April 22, while the crews hang the another new traffic signal mast arm over the travel lane.
Current Construction Activities
Bridge work is underway near the Jordan River this week. Crews will be driving heavy steel bridge supports into the ground in the area beginning Monday, April 26. Residents should expect some increased noise and vibration during this work. Construction activities east of the Jordan River are scheduled to resume in early May. Please watch these updates for additional information.

Ongoing Project Impacts
Crews will continue clearing and placing fill on the west side of the project between the Jordan River and Redwood Road. In the interest of safety, the small section of Jordan River Trail that falls within the project area has been closed. Access along the trail to the north and south will remain open, but there will be no connecting access through the project during construction.
In order to construct the new railroad bridge and subsequently build the roadway beneath the bridge, UTA and UDOT have fully closed 2100 North between 2300 West and Pointe Meadows Drive. This closure will remain in place through Fall of 2011. Motorists should plan to use 1500 North as an alternate route.

Spring Cleanup

Monday, April 19th, 2010
The City of Saratoga Springs will be holding its annual Spring Cleanup. Dumpsters will be placed throughout the City on April 19, 2010 and picked up on April 26, 2010.
Dumpsters will be placed at the following location:
  • Public Works Building (2015 Redwood Road)
  • Saratoga Hills (Grandview Blvd. & Lucas Lane)
  • Pelican Bay-Marina (200 E. Harbor Parkway)
  • Saratoga Springs Development-Marina (625 S. Saratoga Dr.)
  • Eagle Park (Centennial Blvd.)
  • Sunrise Meadows Park (800 West)
  • Loch Lomond Pond (Lakeview Dr.)
  • Harvest Hills Condos (Harvest Moon Dr.)
  • Harvest Hills Park (Providence Dr.)
  • Lake Mountain Estates (Jamaica Way & Mountain Moon Dr.)

Paving Work South of SR-73

Monday, April 19th, 2010
With the power poles now removed from the roadway and temperatures back in the appropriate range for paving, Geneva Rock is scheduled to come back and fill in holes left by the poles. This work is scheduled for Wednesday, April 21, and should take about two days to complete. This paving operation will occur behind existing traffic control and will not impact traffic. Please note that this work is weather dependant. In the event that there is rain or cool temperatures on these days, the paving work will be pushed back until dryer or warmer conditions allow.
In May when spring temperatures permit final paving operations, Geneva Rock will return to add the smooth top layer of asphalt.

Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.

PIoneer Crossing Update: 4/19/10

Monday, April 19th, 2010

I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – With traffic now moved to the south side of Main Street, please remember that lanes are narrowed and all left turns into the business areas between State Street and Kawakami Drive are to be made only at signalized intersections.
April 16-19: Watch for lane shifts on U.S. 89 and Main Street as crews reconstruct the curb, gutter and sidewalks on the north corner of the intersection.
April 19-21: Watch for lane shifts on U.S. 89 and Main Street as crews reconstruct the center median on the north side of the intersection. Intermittent closures of one left hand turn lane onto eastbound Main Street may be required to safely reconstruct median.
April 21-May 5: Watch for lane restrictions and shifts on Main Street at U.S. 89 as crews reconstruct the curb, gutter and sidewalks on the south corner of the intersection.
Ongoing: The right-in turns into Main Street Plaza and the Alpine Shopping Center from westbound Main Street are closed to allow crews to reconstruct the north half of Main Street between U.S. 89 and I-15. The closure will be in place until mid-August. Motorists should use Kawakami Drive to access the shopping centers.
1020 West is closed as crews install utilities down the center of 1020 West and reconstruct the roadway. The closure will be in place through early May. Motorists will need to use 900 West for access to homes and businesses on 1020 West.
Work is underway at the bridge farm location, north of 900 West. Flaggers will be posted at 900 West to guide drivers through the work zone. Work will continue through the night so expect some construction noise.
Work on abutments and bridge support columns for the north bridge of the new Diverging Diamond Interchange (DDI) continues near the interchange.
Ongoing: I-15 will be restricted to two lanes in each direction nightly from 8 p.m. to 6 a.m. for bridge construction and paving. Please expect periodic restrictions at the on- and off-ramps during these hours. Lane restrictions will continue through the spring. Motorists should anticipate moderate travel delays.
Ramps for the northbound on-ramp and southbound off-ramp at American Fork Main Street have been shifted onto the new concrete. Please use caution when entering and exiting the freeway.
I-15 Travel Lane Changes: The I-15 travel lanes near the American Fork Main Street interchange are narrowed to 11 feet and 10.5 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
For information about I-15 CORE construction activities near American Fork Main Street please visit www.i15core.utah.gov.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – Work to set girders for the Mill Pond Bridge is complete. Work on the bridge deck structure continues. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone. This work will continue through spring.
South Area – Work on retaining walls will continue through April.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until mid-summer 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): April 26- Mid-June: 300 East will be closed for utility work and construction of the new intersection. All through traffic will be detoured along Center Street. Other routes are available for area residents affected by the closure.
500 West to 300 East Area (Lehi): Center Street is closed at the Pioneer Crossing intersection for utility work and construction of the new intersection. All through traffic is detoured along 500 West and 1900 South. Other routes are available for area residents affected by the closure. Center Street will reopen April 23.
1100 West to 500 West Area (Lehi): 1100 West is closed for utility work and construction of the new intersection. All through traffic is detoured along 500 West or 2300 West and 1900 South. Other routes are available for area residents affected by the closure. The closure will reopen April 19.
April 23- Mid-June: 500 West will be closed for utility work and construction of the new intersection. All through traffic will be detoured along 1100 West, Center Street and 1900 South. Other routes are available for area residents affected by the closure.
1700 West to 1100 West Area (Lehi): Construction of the trail undercrossing for the future Dry Creek trail continues. The top portion of the trail undercrossing has been poured.
Work on noise walls will continue through early May.
Work will continue on footings and walls for the Dry Creek box culvert through May.
April 26- May 5: 1700 West will be closed near the Pioneer Crossing intersection to allow for crews to place the final layer of asphalt and raise utility manholes. Motorists should use 2300 West.
2300 West to 1700 West Area (Lehi): Work to install utilities will continue. Crews will begin placing top soil in the park strip in early May.
April 19-24: 2300 West will be closed near the Pioneer Crossing intersection to allow for crews to place the final layer of asphalt and raise utility manholes. Motorists should use 1100 West.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Work will begin this week to place top soil in the medians. Crews will begin installing plants and trees in early May.
Jordan River Bridge Area – Crews continue to build the walls for the river bridge. Placement of the concrete bridge deck is complete. Work on the bridge approaches will continue through April.
Work on the Jordan River Parkway Trail crossing at the new Pioneer Crossing bridge continues. Meanwhile, the Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration in early summer.
Redwood Road to Jordan River Area – Work continues on foundations for the permanent signs. Crews will begin paving roadway on Monday and will continue through next week. Work to place curb and gutter will begin next week.
General Project Information General work hours are between 7 a.m. and 5 p.m. Monday through Saturday. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents – especially children – to keep out of the construction area.

2100 North Project Update: 4/15/10

Thursday, April 15th, 2010

The following are planned activities for the coming week. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change. The new signal on Redwood Road is substantially complete, but crews have decided not to activate the signal for the time being. Notice will be given should they need to activate it later.
Current Construction Activities
Work to construct the bridges near the Jordan River has begun. This work includes installing bridge supports and walls. Construction activities east of the Jordan River are scheduled to resume in early May. Please watch these updates for additional information.

Ongoing Project Impacts
Crews will continue clearing and placing fill on the west side of the project between the Jordan River and Redwood Road. Work on the irrigation system continues just east of Redwood Road in preparation for the irrigation season beginning this month. This work will have no impact to traffic. In the interest of safety, the small section of Jordan River Trail that falls within the project area has been closed. Access along the trail to the north and south will remain open, but there will be no connecting access through the project during construction. In order to construct the new railroad bridge and subsequently build the roadway beneath the bridge, UTA and UDOT have fully closed 2100 North between 2300 West and Pointe Meadows Drive. This closure will remain in place through Fall of 2011. Motorists should plan to use 1500 North as an alternate route.

City Marina Closed

Tuesday, April 13th, 2010
The City Marina will be closed starting Wednesday, April 14, 2010 and will remain closed for approximately 2 weeks. Closure is due to construction taking place near the boat ramp and heavy truck traffic needing to move in and out. We apologize for the inconvenience and appreciate your patience in this matter.

Pioneer Crossing Update: 4/12/10

Monday, April 12th, 2010

Project update for the week of April 12, 2010
I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – With traffic now moved to the south side of Main Street, please remember that lanes are narrowed and all left turns into the business areas between State Street and Kawakami Drive are to be made only at signalized intersections.
April 12-19: Watch for lane shifts on U.S. 89 and Main Street as crews reconstruct the curb, gutter and sidewalks on the north corners of the intersection. Intermittent lane closures on westbound Main Street may be required to safely reconstruct the northeast corner.
April 21-May 5: Watch for lane restrictions and shifts on Main Street at U.S. 89 as crews reconstruct the curb, gutter and sidewalks on the south corner of the intersection.
Ongoing: The right-in turns into Main Street Plaza and the Alpine Shopping Center from westbound Main Street are closed to allow crews to reconstruct the north half of Main Street between U.S. 89 and I-15. The closure will be in place until mid-August. Motorists should use Kawakami Drive to access the shopping centers.
Crews are working on storm drain and retaining walls north of the DDI in the park and ride lot on 900 West. Several parking stalls on the northeast end of the lot have been eliminated. Please use caution in the area and watch for construction equipment. 1020 West is closed as crews install utilities down the center of 1020 West and reconstruct the roadway. The closure will be in place through early May. Motorists will need to use 900 West for access to homes and businesses on 1020 West. Work is underway at the bridge farm location, north of 900 West. Crews will be working through the night so expect some construction noise Work on retaining walls for the north bridge of the new Diverging Diamond Interchange (DDI) continues near the interchange.
Ongoing: I-15 will be restricted to two lanes in each direction nightly from 8 p.m. to 6 a.m. for bridge construction and storm drain installation. A third lane will be restricted southbound beginning at 11 p.m. Please expect periodic restrictions at the on- and off-ramps during these hours. Lane restrictions will continue through the spring. Motorists should anticipate moderate travel delays. Ramps for the northbound on-ramp and southbound off-ramp at American Fork Main Street have been shifted onto the new concrete. Please use caution when entering and exiting the freeway.
I-15 Travel Lane Changes: The I-15 travel lanes near the American Fork Main Street interchange are narrowed to 11 feet and 10.5 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones. For information about I-15 CORE construction activities near American Fork Main Street please visit www.i15core.utah.gov.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – Crews are setting girders and working on the bridge walls for the new intersection over the railroad tracks. Settlement of the ground is now complete and work will begin this week to remove the surcharge. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone. This work will continue through spring. Work to set girders for the Mill Pond Bridge is complete.
South Area – Work on retaining walls will continue through April. Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until late spring 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): April 26- Mid-June: 300 East will be closed for utility work and construction of the new intersection. All through traffic will be detoured along Center Street. Other routes are available for area residents affected by the closure.
500 West to 300 East Area (Lehi): Center Street is closed at the Pioneer Crossing intersection for utility work and construction of the new intersection. All through traffic is detoured along 500 West and 1900 South. Other routes are available for area residents affected by the closure. Center Street will reopen April 23.
1100 West to 500 West Area (Lehi): 1100 West is closed for utility work and construction of the new intersection. All through traffic is detoured along 500 West or 2300 West and 1900 South. Other routes are available for area residents affected by the closure. The closure will reopen April 19.
April 23- Mid-June: 500 West will be closed for utility work and construction of the new intersection. All through traffic will be detoured along 1100 West, Center Street and 1900 South. Other routes are available for area residents affected by the closure.
1700 West to 1100 West Area (Lehi): Construction of the trail undercrossing for the future Dry Creek trail continues. The top portion of the trail undercrossing has been poured. Work on signal boxes will continue this week.
Crews are working on noise walls.
Work will begin on footings and walls for the Dry Creek box culvert this week.
April 26- May 5: 1700 West will be closed near the Pioneer Crossing intersection to allow for crews to place the final layer of asphalt and raise utility manholes. Motorists should use 2300 West.
2300 West to 1700 West Area (Lehi): Work will finish pouring sidewalks on Monday. Irrigation work will continue through late April.
April 19-24: 2300 West will be closed near the Pioneer Crossing intersection to allow for crews to place the final layer of asphalt and raise utility manholes. Motorists should use 1100 West.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Work on utility lines and irrigation will continue.
Jordan River Bridge Area – Crews continue to build the walls for the river bridge. Placement of the concrete bridge deck is complete. Work on the bridge approaches will continue through April. Work on the Jordan River Parkway Trail crossing at the new Pioneer Crossing bridge continues. Meanwhile, the Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration in early summer.
Redwood Road to Jordan River Area – Crews are working on foundations for the permanent signs. Crews will begin placing topsoil in the park strip this week. General Project Information General work hours are between 7 a.m. and 5 p.m. Monday through Saturday. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents – especially children – to keep out of the construction area.

Road Closure: Lehi Fairfield Road

Thursday, April 8th, 2010

Please note that the Lehi Fairfield road near Pony Express Parkway (Eagle Mountain) and 800 West (Saratoga Springs) will be closed beginning Monday, April 12, 2010 and will not open up until around April 26, 2010. Road is closed due to a new roadway in the area being worked on. We apologize for the inconvenience and appreciate your patience in this matter.

2100 North Project Update: 4/8/10

Thursday, April 8th, 2010

The following are planned activities for the coming week. Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.
As a reminder, crews are at work this week placing the new traffic signal on Redwood Road for the future intersection with 2100 N. The new signal is scheduled to be active in mid-April. (see below for associated traffic impacts on Redwood Rd. ) Current Construction Activities
For safety reasons, one northbound lane on Redwood Road will be closed for several hours on Wednesday and Thursday of next week, April 14-15, while the crews hang the new traffic signal mast arm over the travel lane. Construction activities east of the Jordan River are scheduled to resume in late April/early May. Please watch these updates for additional information.

Ongoing Project Impacts
Crews will continue clearing and placing fill on the west side of the project between the Jordan River and Redwood Road. Work on the irrigation system continues just east of Redwood Road in preparation for the irrigation season beginning this month. This work will have no impact to traffic. In the interest of safety, the small section of Jordan River Trail that falls within the project area has been closed. Access along the trail to the north and south will remain open, but there will be no connecting access through the project during construction. In order to construct the new railroad bridge and subsequently build the roadway beneath the bridge, UTA and UDOT have fully closed 2100 North between 2300 West and Pointe Meadows Drive. This closure will remain in place through Fall of 2011. Motorists should plan to use 1500 North as an alternate route.