I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – Work continues on the traffic signal at Kawakami Drive. The new signal will be operational by Nov. 30.
Crews are placing the final concrete and asphalt segments leading up to the new interchange bridge. Traffic will be diverted onto the bridge Nov. 30. Once motorists have been switched onto the new bridge, crews will build new ramp connections from I-15 southbound and to I-15 northbound. Beginning Nov. 30 through Dec. 3, access to the on-ramp to I-15 northbound from the west side of the interchange will be restricted. Motorists needing to connect to I-15 northbound via the on-ramp from the west will need to use Mill Pond Road to Lehi Main Street as an alternative route.
Ramp closures:Dec. 2-3: The northbound on- and southbound-off ramp at I-15 will be closed at night from approximately 8 p.m. Wednesday, Dec. 2 to 7 a.m. the following morning. Motorists will need to use the I-15 interchanges at Lehi Main Street or 500 East in American Fork as alternative routes.
Bridge demolition:Dec. 5-6: I-15 will be closed beginning at 10 p.m. Saturday until 9:30 a.m. Sunday, while crews demolish the old interchange bridge at American Fork Main Street. Motorists will be diverted over the on- and off-ramps at the interchange. Please anticipate moderate to heavy travel delays between 10 p.m. and midnight. Please use caution when exiting and entering the interstate and expect slight travel delays as trucks, heavy equipment and construction crews are working nearby. Flaggers are posted to guide motorists through the construction area.
I-15 Travel Lane Changes: The travel lanes along I-15 near the American Fork Main Street interchange have been narrowed to 11 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – The footings for the retaining wall for the north embankment of the Mill Pond Bridge is in place. Crews are building the retaining walls and placing embankment. Trucks will be working well into the night. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone. This work will continue through mid-January.
Nov. 30 – Dec 21. 900 West in American Fork will be closed for culinary and irrigation line installation. Motorists will need to use 1020 West to access area homes and businesses and the park-and-ride lot.
South Area – Crews will finish placing additional material on the embankment through the first week in December. Construction of the bridge support walls (abutments) will begin by mid-December.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until late spring 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): Utility and irrigation work continues.
500 West to 300 East Area (Lehi): Crews will finish utility line connections, utility access and irrigation work during the next few weeks.
1100 West to 500 West Area (Lehi): There is minimal work within this area. Crews will prepare the roadway area for curb, gutter and sidewalk.
1700 West to 1100 West Area (Lehi): The crossing for Dry Creek is in place. Construction of the trail undercrossing for the future Dry Creek trail is underway. Work on utility accesses continues.
2300 West to 1700 West Area (Lehi): Crews will build the base layers for the sidewalk. Sidewalk will be placed as weather allows.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Installation of utility accesses, storm drain lines and landscaping will continue through mid-December.
Jordan River Bridge Area – Placement of forms and rebar framework for the river bridge continues. The concrete bridge deck will be placed within two weeks.
The 60-inch waterline is in place. Crews will begin restoring the embankments along the river and removing the temporary bridge crossing by mid-December.
The Jordan River Parkway Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration next spring.
Redwood Road to Jordan River Area – Crews will install sprinkler lines in this area. Signal poles and street lights will be installed towards the middle of December. Sidewalk construction continues.
General Project Information General work hours are between 7 a.m. and 6 p.m. Monday through Saturday. For specific construction tasks there will be night work. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents to keep out of the construction area. If you have questions or would like additional information about this project, feel free to contact us at 1.877.222.3757, via email at access@utah.gov, or visit the project Web site at udot.utah.gov/pioneer.