Archive for November, 2009

Pioneer Crossing Update: 11/30/09

Monday, November 30th, 2009
**Note: Although several sections of the concrete pavement have been placed, work is not complete. Please do not drive on the new road.
I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – Work continues on the traffic signal at Kawakami Drive. The new signal will be operational by Nov. 30.
Crews are placing the final concrete and asphalt segments leading up to the new interchange bridge. Traffic will be diverted onto the bridge Nov. 30. Once motorists have been switched onto the new bridge, crews will build new ramp connections from I-15 southbound and to I-15 northbound. Beginning Nov. 30 through Dec. 3, access to the on-ramp to I-15 northbound from the west side of the interchange will be restricted. Motorists needing to connect to I-15 northbound via the on-ramp from the west will need to use Mill Pond Road to Lehi Main Street as an alternative route.
Ramp closures:Dec. 2-3: The northbound on- and southbound-off ramp at I-15 will be closed at night from approximately 8 p.m. Wednesday, Dec. 2 to 7 a.m. the following morning. Motorists will need to use the I-15 interchanges at Lehi Main Street or 500 East in American Fork as alternative routes.
Bridge demolition:Dec. 5-6: I-15 will be closed beginning at 10 p.m. Saturday until 9:30 a.m. Sunday, while crews demolish the old interchange bridge at American Fork Main Street. Motorists will be diverted over the on- and off-ramps at the interchange. Please anticipate moderate to heavy travel delays between 10 p.m. and midnight. Please use caution when exiting and entering the interstate and expect slight travel delays as trucks, heavy equipment and construction crews are working nearby. Flaggers are posted to guide motorists through the construction area.
I-15 Travel Lane Changes: The travel lanes along I-15 near the American Fork Main Street interchange have been narrowed to 11 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – The footings for the retaining wall for the north embankment of the Mill Pond Bridge is in place. Crews are building the retaining walls and placing embankment. Trucks will be working well into the night. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone. This work will continue through mid-January.
Nov. 30 – Dec 21. 900 West in American Fork will be closed for culinary and irrigation line installation. Motorists will need to use 1020 West to access area homes and businesses and the park-and-ride lot.
South Area – Crews will finish placing additional material on the embankment through the first week in December. Construction of the bridge support walls (abutments) will begin by mid-December.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until late spring 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): Utility and irrigation work continues.
500 West to 300 East Area (Lehi): Crews will finish utility line connections, utility access and irrigation work during the next few weeks.
1100 West to 500 West Area (Lehi): There is minimal work within this area. Crews will prepare the roadway area for curb, gutter and sidewalk.
1700 West to 1100 West Area (Lehi): The crossing for Dry Creek is in place. Construction of the trail undercrossing for the future Dry Creek trail is underway. Work on utility accesses continues.
2300 West to 1700 West Area (Lehi): Crews will build the base layers for the sidewalk. Sidewalk will be placed as weather allows.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Installation of utility accesses, storm drain lines and landscaping will continue through mid-December.
Jordan River Bridge Area – Placement of forms and rebar framework for the river bridge continues. The concrete bridge deck will be placed within two weeks.
The 60-inch waterline is in place. Crews will begin restoring the embankments along the river and removing the temporary bridge crossing by mid-December.
The Jordan River Parkway Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration next spring.
Redwood Road to Jordan River Area – Crews will install sprinkler lines in this area. Signal poles and street lights will be installed towards the middle of December. Sidewalk construction continues.
General Project Information General work hours are between 7 a.m. and 6 p.m. Monday through Saturday. For specific construction tasks there will be night work. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents to keep out of the construction area. If you have questions or would like additional information about this project, feel free to contact us at 1.877.222.3757, via email at access@utah.gov, or visit the project Web site at udot.utah.gov/pioneer.

Public Works Administrative Assistant Needed!

Monday, November 23rd, 2009
The City of Saratoga Springs is currently looking to hire a part-time Public Works Administrative Assistant. Interested persons should fill out a City employment application. For a detailed job description click here.

Pioneer Crossing Update: 11/23/09

Monday, November 23rd, 2009
I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – Signal work continues at Kawakami Drive. Crews will set poles at the north side of intersection before Thanksgiving. The new signal will be operational by Nov 30. Crews are installing drainage basins and curb and gutter along the south side of Main Street as they prepare to divert traffic onto the south side of Main Street. The bridge transitions have been poured and crews are placing the final concrete and asphalt segments leading up to the new interchange bridge. Traffic will be diverted onto the bridge beginning Nov. 30. Once motorists have been switched onto the new bridge, Crews will build new ramp connections from I-15 southbound and to I-15 northbound. Each of these ramps will be closed during the night of Dec. 1.The old interchange bridge will be removed the first weekend in December (Dec. 5-6). Nov. 23. I-15 southbound will be restricted to three lanes in each direction (the Express Lanes will be closed) at the interchange to American Fork Main Street, from 8 p.m. to 11 p.m. for barrier work. Motorists should expect moderate travel delays. Please use caution when exiting and entering the interstate and expect slight travel delays as trucks, heavy equipment and construction crews are working nearby. Flaggers are posted to guide motorists through the construction area.
I-15 Travel Lane Changes: The travel lanes along I-15 near the American Fork Main Street interchange have been narrowed to 11 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – Crews have placed the footings for the retaining wall for the north embankment of the Mill Pond Bridge. Crews will build the retaining walls and place embankment. Trucks will be working well into the night. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone. This work will continue through mid-January. Crews have widened 80 North (between 1020 and 900 West) to improve traffic flow within this area.
South Area – The retaining walls are in place. Crews will continue to place additional material on the embankment through the first week in December. Construction of the bridge support walls (abutments) will begin the first of December.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until late spring 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): Crews have placed the first concrete sections of the road between 300 East and the new bridge at Mill Pond Road. Paving operations are on hold until spring 2010. Utility and irrigation work continues.
500 West to 300 East Area (Lehi): Paving of this area is on hold until spring 2010. Crews will finish utility line connections and irrigation work during the next few weeks.
1100 West to 500 West Area (Lehi): In December, crews will prepare the roadway area for curb, gutter and sidewalk.
1700 West to 1100 West Area (Lehi): Excavation for the trail undercrossing for the future Dry Creek trail is underway. Crews are installing gas lines in this area.
The intersection at 1700 West is open.
2300 West to 1700 West Area (Lehi): Crews will build the base layers for the sidewalk. Sidewalk will be placed as weather allows.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Installation of utility accesses, storm drain lines and landscaping will continue through mid-December.
Jordan River Bridge Area – Crews are building the forms and rebar framework for the bridge transition areas and bridge deck. The concrete bridge deck will be placed by mid-December.
Crews will finish installing the 60-inch water line under the Jordan River before Thanksgiving. Once the pipeline is installed, crews will remove the temporary bridge crossing and restore the embankments along the river. The Jordan River Parkway Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration next spring.
Redwood Road to Jordan River Area – The underground work for the traffic signal at Redwood Road and street lighting is complete. Crews will set signal poles and street lights towards the middle of December. Sidewalk construction continues.
General Project Information General work hours are between 7 a.m. and 6 p.m. Monday through Saturday. For specific construction tasks there will be night work. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents to keep out of the construction area.
If you have questions or would like additional information about this project, feel free to contact us at 1.877.222.3757, via email at access@utah.gov, or visit the project Web site at udot.utah.gov/pioneer.

Redwood Road Update: 11/19/09

Thursday, November 19th, 2009
Rocky Mountain Power continues to work south of SR-73 removing poles and placing new ones. As soon as their poles are moved, SR-68 crews plan to fill the holes, patch the surrounding area and make preparations for the removal of barrels so traffic can flow normally over the winter.

General Impacts south of SR-73
Due to cold weather conditions and utility delays, the contractor will need to come back to finalize some paving in the spring. Work in the spring should last only a few weeks and have limited impacts. Crews will continue working on the sidewalk and concrete driveways in the southeast corner of the Crossroads intersection this week. Where possible, only one driveway at a time will be worked on in order to maintain access to the businesses in the area. Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense. Crews continue on several clean up items and final adjustments throughout the project, including driveways, landscaping, fence, placing road signs and reflectors, and raising manholes to the level of the road. In order for crews to safely work on these items, some brief access interruptions and lane shifts may occur.

Please note that due to weather, project conflicts, or equipment/supply issues, schedules are subject to change.

More Information
For additional project information, visit www.udot.utah.gov/sr-68south. For specific questions or concerns, contact the Public Information Team at sr68info@langdongroupinc.com or 801-455-3116.

Pioneer Crossing Update: 11/16/09

Monday, November 16th, 2009
I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – Signal work continues at Kawakami Drive and at the new off-ramp from I-15 northbound. Foundations will be placed on the north side and the new signal will be operational by Dec. 1. Crews will install drainage basins and curb and gutter along the south side of Main Street. All traffic will be diverted onto the south side of Main Street beginning Nov. 30. At the new bridge, crews have placed concrete at the center and west transitions of the bridge. The transition on the east side of the bridge will be complete by the end of the week. The safety walls (parapets) will also be complete by the end of the week. During the next two weeks, crews will place the final concrete and asphalt segments leading up to the new interchange bridge. Traffic will be diverted onto the bridge beginning Nov. 30. The old interchange bridge will be removed the first weekend in December. Please use caution when exiting and entering the interstate and expect slight travel delays as trucks, heavy equipment and construction crews are working nearby. Flaggers are posted to guide motorists through the construction area.
I-15 Travel Lane Changes: The travel lanes along I-15 near the American Fork Main Street interchange have been narrowed to 11 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
Mill Pond Road Area in Lehi to American Fork Main St.: North Area – Crews will begin building footings for the retaining wall for the north embankment of the Mill Pond Bridge. Beginning the week of Nov. 23, crews will build the retaining walls and place embankment. Trucks will be working well into the night. As trucks will be accessing this area, motorists should anticipate moderate travel delays. Flaggers will be posted to guide drivers through the work zone.
Between 900 and 1020 West in American Fork, crews will widen 80 North to improve traffic flow within this area. Please use caution as heavy equipment is working nearby.
South Area – Construction of the embankment and retaining walls for the new bridge is nearly complete. Crews are hauling in fill material and building the retaining walls. Motorists should expect moderate travel delays due to trucks accessing the work zone. Flaggers are posted to guide traffic through the area. This operation will be complete by December 4.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until late spring 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): Crews have placed the first concrete sections of the road between 300 East and the new bridge at Mill Pond Road.
500 West to 300 East Area (Lehi): Construction of utility access boxes and other utility lines (culinary water, irrigation and fiber conduit) continues between 500 West and Center Street. Towards the middle of the week, crews will pave new segments of the road between 500 West and Center Street. Paving operations will be during the day while crews cut the concrete at specific locations approximately 10-to-12 hours after. As the paving and concrete cutting process is noisy, please expect some inconvenience for a couple of days during this work.
1100 West to 500 West Area (Lehi): The initial concrete segments have been placed between 1100 West and 500 West. Installation of irrigation lines is complete.
1700 West to 1100 West Area (Lehi): Installation of the 60-inch water line in the Dry Creek area is complete. Crews are working on utility accesses. Excavation for the trail undercrossing for the future Dry Creek trail is underway. At the intersection of 1700 West, crews have placed curb, gutter and sidewalk. Utility access covers have been placed and the intersection will open by Nov. 20.
2300 West to 1700 West Area (Lehi): Minimal work in this area. Sidewalk should be placed during the first part of December.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Installation of utility accesses and storm drain and irrigation lines continues.
Jordan River Bridge Area – Crews are building the forms and rebar framework for the bridge transition areas and bridge deck. The concrete bridge deck will be placed mid-December.
Installation of the 60-inch water line under the Jordan River continues. This work will be complete before Thanksgiving. The Jordan River Parkway Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi. The trail will re-open in its new configuration next spring.
Redwood Road to Jordan River Area – Traffic signal work for the new intersection with Redwood Road continues. Construction of sidewalks within this area are nearly complete.
General Project Information General work hours are between 7 a.m. and 6 p.m. Monday through Saturday. For specific construction tasks there will be night work. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents to keep out of the construction area.

Redwood Road Update: 11/12/09

Thursday, November 12th, 2009
Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Crews will begin working on the sidewalk and concrete driveways in the southeast corner of the Crossroads intersection this week. Where possible, only one driveway at a time will be worked on in order to maintain access to the businesses in the area.

Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Due to cold weather conditions and utility delays, the contractor will need to come back to finalize some paving in the spring. Work in the spring should be complete within three weeks time and have limited impacts. Activities in Segment 1 this week include installing sidewalk and paving and will be ongoing for several more weeks. Paving activities are weather dependent and final paving is dependent on utility relocation progress. Rocky Mountain Power continues to be at work in this area removing poles and placing new ones for several more weeks. Once the poles are moved, crews plan to fill the holes and make preparations for the removal of barrels and for traffic to flow normally over the winter. Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense. Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs.

General Impacts north of SR-73
Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense.
Crews continue on several clean up items and final adjustments throughout the project, including driveways, landscaping, fence, placing road signs and reflectors, and raising manholes to the level of the road. In order for crews to safely work on these items, some brief access interruptions and lane shifts may occur.

1st Annual Saratoga Springs Christmas Tree Lighting

Thursday, November 12th, 2009

Come join the Civic Events in the 1st Annual Saratoga Springs Christmas Tree Lighting.

Date: Monday, November 30th
Time: 6:30 PM
Location: at the city offices (1307 N. Commerce Dr.)

Program by Harvest Elementary Spanish Immersion Choir and Westlake High School Choir. Santa will be there with a treat for the first 200 kids. Come and start a new tradition with us as we kick of the Christmas season in Saratoga Springs.

Pioneer Crossing Update: 11/9/09

Monday, November 9th, 2009
**Note: Although several sections of the concrete pavement have been placed, work is not complete. Please do not drive on the new road.
I-15 Interchange at American Fork Main Street: Main Street Area (East of I-15) – Signal work continues at Kawakami Drive and at the new off-ramp from I-15 northbound. Crews are paving various segments of the road and on-and off-ramps at the interchange. Curb and gutter work continues in preparation for switching traffic onto the south side of Main Street November 30.
Through November: Main Street remains restricted to one lane in each direction from State Street to I-15 while crews reconstruct the south half of Main Street. Motorists will be able to access businesses along the south side of Main Street at Kawakami Drive. Motorists should expect moderate to heavy travel delays. All traffic will be moved to the south side of Main Street around the end of November. In the area of the on-ramp to northbound I-15, crews are building retaining walls.
Nov. 9: The existing on-ramp to I-15 southbound will be closed permanently. A temporary on-ramp will be opened near the 900 West intersection. 900 West will be modified to allow right turns only. Motorists will be diverted to 1020 West for all left turns in and out of the area. Once traffic has been moved over to the south half of the road November 30, turning restrictions at 900 West will be removed. At the new bridge, crews are building the rebar framework for the remainder of the bridge deck. They are also placing concrete at the transition areas, building safety walls (parapets) and finishing the bridge deck. Please use caution when exiting and entering the interstate and expect slight travel delays as trucks, heavy equipment and construction crews are working nearby. Flaggers are posted to guide motorists through the construction area.
I-15 Travel Lane Changes: The travel lanes along I-15 near the American Fork Main Street interchange have been narrowed to 11 feet and the speed limit is reduced to 55 mph. Please remember, fines for speeding violations are doubled in construction zones.
Mill Pond Road Area (Lehi to I-15 in American Fork): North Area – The south half of the road between I-15 and Mill Pond Road has been paved. Crews will place sidewalk as they prepare to divert traffic onto a segment of the new road by the end of November.
South Area – Construction of the embankment and retaining walls for the new bridge continues. Crews are hauling in fill material and building the retaining walls. Motorists should expect moderate travel delays due to these trucks accessing the work zone. Flaggers are posted to guide traffic through the area. This operation will continue through November.
Mill Pond Road south of the intersection with 8020 North in Lehi (south of the UPRR tracks) will remain closed until late spring 2010. Residents traveling north and south in this area can use 200 South to 300 West in American Fork or 300 East to 700 South in Lehi as alternatives.
300 East to Mill Pond Area (Lehi): Crews are preparing the area for the concrete pavement. The first segment of the road within this area should be paved by the end of the week.
Nov. 9 – 10. 300 East will be closed for additional utility work. Motorists will need to use Center Street or 500 West as alternative routes.
500 West to 300 East Area (Lehi): Construction of utility access boxes and other utility lines (culinary water, irrigation and fiber conduit) continues between 500 West and Center Street. Crews will pave new segments of the road within this area during the day and cut the concrete at specific locations approximately 10 to 12 hours after. As the paving and concrete cutting process is noisy, please expect some inconvenience for a couple of days during this work.
Please use caution and be courteous when crossing the work zone at Center Street as traffic has been diverted onto temporary pavement.
1100 West to 500 West Area (Lehi): The initial concrete segments have been placed between 1100 West and 500 West and the concrete is curing. Installation of irrigation lines continues.
1700 West to 1100 West Area (Lehi): Installation of the 60-inch water line in the Dry Creek area will be complete by the end of the week. The intersection has been paved and crews will place sidewalk and traffic signal poles.
Present to mid-Nov.: 1700 West remains closed for reconstruction of the intersection. Motorists will be detoured to 2300 West as the alternative route. Pedestrians will be diverted around the work area. Flaggers will be posted to help pedestrians cross the work zone safely.
2300 West to 1700 West Area (Lehi): Additional sidewalk will be placed towards the end of November.
Redwood Road to 2300 West Area (Lehi/ Saratoga Springs): Jordan River Bridge to 2300 West – Crews continue to place sidewalk along the roadway through 2300 West. The concrete has been placed just east of the Jordan River. Crews will return at a later date to place the shoulder areas of the road, curb, gutter and sidewalk. Installation of utility accesses and lines continues.
Jordan River Bridge Area – Crews are building the forms and rebar framework for the bridge transition areas and bridge deck. The concrete bridge deck will be placed towards the end of November.
Installation of the 60-inch water line under the Jordan River is underway. This work will be complete before Thanksgiving.
The Jordan River Parkway Trail remains closed approximately one mile north of the trailhead at Wetlands Park in Saratoga Springs. Please do not attempt to cross through the work zone as there are large dump trucks driving through the area. Trail users can access the trail at Willow Park in Lehi.
Redwood Road to Jordan River Area – Construction of sidewalks and the raised median continues.
General Project Information General work hours are between 7 a.m. and 6 p.m. Monday through Saturday. For specific construction tasks, such as concrete paving, there will be night work. Please use caution and slow down as you travel through the construction area as crews, large trucks and other heavy equipment are working nearby. For the safety of the public, we encourage all area residents – especially children – to keep out of the construction area.
If you have questions or would like additional information about this project, feel free to contact us at 1.877.222.3757, via email at access@utah.gov, or visit the project Web site at udot.utah.gov/pioneer.

Redwood Road Update: 11/5/09

Thursday, November 5th, 2009

Segment 2 – Beginning south of Camp Williams and ending just south of the intersection at SR-73 in Saratoga Springs.
Crews will continue working on the storm drain on the southeast corner of the Crossroads. This work will take place in the shoulder with some intermittent traffic shifts.

Segment 1 – Beginning south of the intersection at SR-73 and ending at 400 S. in Saratoga Springs.
Due to cold weather conditions and utility delays, the contractor will need to come back to finalize some paving in the spring. Work in the spring should be complete within three weeks time and have limited impacts. Activities in Segment 1 this week include storm drain tie-ins, median work, and paving and will be ongoing for several more weeks. Paving activities are weather dependent and final paving is dependent on utility relocation progress. Rocky Mountain Power continues to be at work in this area removing poles and placing new ones for several more weeks. Once the poles are moved, crews plan to fill the holes and make preparations for the removal of barrels and for traffic to flow normally over the winter. Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense.
Work on the Pioneer Crossing project continues in the vicinity of 400 N. in Saratoga Springs.
If you have questions about the Pioneer Crossing project, please contact their Public Information Team directly:
Hotline: 877-222-3757
Email: access@utah.gov

General Impacts north of SR-73
Approved roadside mailboxes continue to be placed along the project. For safety reasons, federal regulations dictate that these new boxes be placed on breakaway posts. Please note, residents should not alter these boxes after they are installed. Any alterations are at risk of removal and replacement at the property owners’ expense. Crews continue on several clean up items and final adjustments throughout the project, including driveways, landscaping, fence, placing road signs and reflectors, and raising manholes to the level of the road. In order for crews to safely work on these items, some brief access interruptions and lane shifts may occur.

Unofficial General Election Results-2009

Wednesday, November 4th, 2009

Unofficial General Election Results-2009

Mayor
Jeff D. Francom 594
Ludmya (Mia) B. Love 861*

Councilmembers
Michael D.S. McOmber 764*
Jim Miller 814*
Michael R. Simpson 490
Cecil E. Tuley 751

Saratoga Precinct 01
Total Votes Cast 1034
Total Registered Voters 4190

Saratoga Precinct 02
Total Votes Cast 427
Total Registered Voters 2149

Combined Total Votes Cast: 1461
Combined Total Registered Voters: 6339
% Voter turnout: 23